School or hospital · Chaklala Scheme III, Rawalpindi · 2025

120 kW on-grid system for a school campus

Classrooms, labs and fans run on the sun during school hours.

  • A campus with a brick building, a green sports pitch and two large solar canopies over a car park, seen from above
  • Rows of blue solar panels on a flat rooftop under a bright blue sky, with domed brick buildings behind
  • A worker in a red hard hat, safety vest and gloves kneels on a roof fixing a solar panel frame

The system in numbers

Solar system
120.51kW
Panels
206
Monthly bill: Rs 9 lakh before, Rs 4.7 lakh after
48% lower
To pay for itself, roughly
2.4years

How it went

A school campus with 1,800 students uses almost all of its electricity between 7:30 am and 2 pm: fans, lights, three computer labs and a water cooler on every floor. That is exactly when solar produces.

We installed 206 panels across the flat roofs of three blocks, with three on-grid inverters and a separate breaker for each block, so one can be serviced while the others keep working. The work was done over the winter break so no class was disturbed.

The system is above 25 kW, so we prepared the NEPRA application as well as the IESCO paperwork. In the summer holidays the spare power goes to the grid under net billing.

Ask for a system like this

The saving pays several teachers' salaries every month, and not one school day was lost to the installation.

Administrator, school campus, Rawalpindi